Welcome to the consultation page for the proposed repowering of the wind turbine at Manor House Farm, Meaux Lane, Routh, Beverley, HU17 9SR.

What is the project?

The proposed development is a turbine repowering of an Enercon E33 with an Enercon E53 at Manor House Farm.

A message from the farm

"HN Sinkler & Son has been at Manor House Farm since 1946. We now have our 5th generation in the family business, alongside 12 staff members, all of whom are local to the farm. Over the past 80 years, we’ve done a wide range of farming, from sheep and cattle to free-range hens for eggs, as well as thriving arable land. Because our operations are so busy, the farm demands a lot of electricity. So, it’s time to repower our turbine.”

WHY?

The farm has high energy demands, and this is only expected to increase as the business continues to develop. Manor House Farm is a mixed agricultural business involving free-range egg production and arable farming, alongside an on-site feed mill that supplies the farm and two other sites operated by the business. To operate efficiently on a daily basis – supporting the running of the poultry buildings, grain drying, and feed production – reliable energy is crucial.

As the business grows and moves toward greater electrification, including making the feed mill fully electric, on-site electricity demand will escalate. The existing turbine already contributes to the farm’s energy needs, but upgrading to a newer, more efficient turbine would allow the farm to generate more renewable electricity and better support its future operations.

The proposal is about investing in the long-term future of Manor House Farm. The electricity generated will primarily support the wider agricultural business, with a combination of electricity used on-site and surplus energy exported to the grid. Income from exported electricity will contribute to the cost of upgrading the turbine, supporting the farm’s long-term viability while allowing the business to operate in a more sustainable way.

WHO'S INVOLVED?

Cogeo Planning & Environmental Services Ltd

Consultants providing planning and environmental assessments. 

Rengineers B.V.

Deployment partner providing refurbished turbines and full operational support.

We’re working together to ensure the new turbine is designed and planned to be efficient, environmentally responsible and suitable for the site.

WHAT'S CHANGING?

The new turbine will be an efficient three-bladed model, with a small shift in position. We’re doing this to safely keep the turbine away from hedges while improving efficiency and reliability.

The upgraded model is designed for long-term performance and delivers more than double the output. It will integrate well with the surrounding landscape and existing renewable energy developments, helping increase local renewable energy generation. The changes are modest, but the benefits are significant: better reliability, more energy and easier maintenance.

Comparing the new turbine

DetailExisting 1 x Enercon E33Proposed 1 x Enercon E53
Hub Height
37 m

60 m

Rotor Diameter
33 m

53 m

Tip Height
53.5 m

86.5 m

Access
Existing access track to the turbine

Existing access track to the turbine

Output
330kW

800kW

Impact on Nearby Properties

We understand how important it is that this proposal respects nearby residents. Protecting residential amenity is always one of our top priorities. The new turbine will be carefully positioned to avoid issues like noise or shadow flicker. We’ve already carried out a detailed, desk-based Noise Assessment to make sure the turbine complies with strict industry standards and, importantly, gives neighbours peace of mind. Our Shadow Flicker Assessment identified one property that is affected, but it is within daily and annual limits, so it should not cause annoyance.

What stage is the development at?

The Cogeo team has completed the screening process. The council has confirmed that this project will not require an EIA application. We are now progressing with the full planning application, which will address all the points raised in the council’s screening process.

Project Documents

Location Plan
View Location Plan
Existing Site Plan
View Existing Site Plan
Site Plan
View Site Plan
Turbine Elevation Plan
View Turbine Elevation Plan

FAQs

Will it be noisy?

No. Our Noise Assessment found that the turbine will not be noisy for residents.

What happens in extreme weather?

The turbine is designed to automatically shut down during very high wind speeds. This is a safety feature and ensures the turbine poses no danger to people or property.

Will construction impact traffic?

The turbine will be transported outside of peak traffic times, with transportation specialists managing the process to avoid disruption. The turbine itself will be built in just two days, with other preparatory works taking place over the six weeks beforehand.

What will it look like?

The turbine will be 33 metres taller than the existing turbine. We’ve produced a photo below to indicate what it will look like.

Visualisations

    We want to hear from you

    This consultation hub is about keeping our neighbours informed and involved. If you have any questions, feedback or comments about the proposal, we’d love to hear from you. Please complete the form below.

    The Project Team will track these comments and respond as required.

    ENQUIRY FORM

    Invalid email address.
    Invalid Input
    Do you accept the Privacy Statement(*)
    Do you accept the Privacy Statement
    Please select an option

    Form Privacy Statement

    By completing this form you are agreeing that we can hold and process your personal data in relation to this consultation exercise.

    • We will only share your personal data with the planning team for planning evaluation purposes only.
    • Your identifiable, personal data will not be used for any other purposes without your consent.